Bionol Clearfield

Pipeline Project

Preliminary Project Schedule*

Activity Schedule
Community Dialogue Ongoing
Open House Meetings May 29, 2008
Route Selection May - August 2008
FERC Application Filed October 6, 2008
Permits Approved December 2008 - April 2009
FERC Approval February 2009
Construction April - August 2009
Plant In-service January 2010

* As requested by T.W. Phillips (Subject to change)